Question

The beta distribution is used in project management to:

A) determine which activity should be crashed.

B) calculate the probability that a project will be completed within its budget.

C) calculate expected activity times.

D) calculate slack for activities on the critical path.

E) none of the above

Answer

This answer is hidden. It contains 50 characters.