Question

The correct sequence from longest to smallest duration scheduling is

A) capacity planning, aggregate planning, master schedule, short-term schedule

B) aggregate planning, capacity planning, master schedule, short-term schedule

C) master schedule, capacity planning, aggregate planning, short-term schedule

D) master schedule, aggregate planning, capacity planning, short-term schedule

E) None of the above is correct