The cost performance index (CPI):
a. indicates that a project is under budget if CPI is less than one.
b. can be used to estimate the projected cost of completing the project.
c. indicates that the planned and actual costs are equal if CPI is more than one.
d. is the ratio of earned value to planned value.

Answer

This answer is hidden. It contains 1 characters.