Question

The critical path for the network activities shown below is __________ with duration __________.


Activity Duration Immediate Predecessors
A 2 --
B 4 --
C 6 A,B
D 1 A,B
E 2 B,C,D

A) A-D-E; 5

B) B-E; 6

C) B-D-E; 7

D) A-C-E; 10

E) B-C-E; 12