The first unit of a product took 900 hours to build and the learning curve is 90%. How long will it take to make the first 3 units? (Use Table E.3)

A) less than or equal to 2,470 hours

B) from 2,470 to 2,472 hours

C) from 2,472 to 2,475 hours

D) from 2,475 to 2,478 hours

E) from 2,478 to 2,481 hours

Answer

This answer is hidden. It contains 1 characters.