The following information relating to a company's overhead costs is available. Based on this information, the total overhead variance is:


Budgeted fixed overhead rate per machine hour $0.50
Actual variable overhead $73,000
Budgeted variable overhead rate per machine hour $2.50
Actual fixed overhead $17,000
Budgeted hours allowed for actual output achieved 32,000

Based on this information, the total overhead variance is:
A. $7,000 favorable.
B. $6,000 favorable.
C. $1,000 unfavorable.
D. $6,000 unfavorable.
E. $1,000 favorable.