Question

The following information relating to a company's overhead costs is available.
Budgeted fixed overhead rate per machine hour $0.50
Actual variable overhead $73,000
Budgeted variable overhead rate per machine hour $2.50
Actual fixed overhead $17,000
Budgeted hours allowed for actual output achieved 32,000

Based on this information, the total overhead variance is:
A.$7,000 favorable.
B.$6,000 favorable.
C.$1,000 unfavorable.
D.$6,000 unfavorable.
E.$1,000 favorable.

Answer

This answer is hidden. It contains 206 characters.