The following six jobs are to be scheduled on a single machine:

Job123456
Processing time (min.)80130210120150110

Suppose the jobs are processed in shortest processing time order. Compute the average flowtime after each job is completed. Round your answer to two decimal places.

a. 401.67

b. 391.97

c. 416.67

d. 422.67