Question

The jobs listed below need to be completed. Assume that it is now day 140. If the jobs are sequenced according to the longest processing time rule, what is the lateness of job A?


Job Processing Time (days) Job due date (days)
A 20 180
B 30 200
C 10 175
D 16 230
E 18 210

A) 0.0 days

B) 24.0 days

C) 7.4 days

D) 10.0 days

E) 11.6 days

Answer

This answer is hidden. It contains 22 characters.