The jobs listed below needed to be completed. Assume that it is now day 140. If the jobs are sequenced according to longest processing time rule, what is the lateness of job A?


Job Processing Time (days) Job due date (days)
A 20 180
B 30 200
C 10 175
D 16 230
E 18 210

A) 0.0 days

B) 24.0 days

C) 7.4 days

D) 10.0 days

E) 11.6 days

Answer

This answer is hidden. It contains 1 characters.