Question

The project organization works best when which of the following conditions are satisfied?

I. Work tasks can be defined with a specific goal and deadline.

II. The job is typical and familiar to the existing organization.

III. The work contains interrelated tasks requiring specialized skills.

IV. The project is temporary but unimportant to long-term organizational success.

V. The project cuts across organizational lines.

A) I, II, III, IV, V

B) None of the above conditions need to be satisfied.

C) I, III, V

D) I, II, III, V

E) I, III, IV, V

Answer

This answer is hidden. It contains 28 characters.