Question

The quality manager for Microelectronics, Inc., is concerned about the quality of the batch of several thousand Z-box games which his company is about to ship. If the cost of replacing a defective Z-box game once it has been shipped is $5.00, while the cost of complete (100 percent) inspection prior to shipment is $.20 each, at what point is he indifferent between complete inspection and shipment without inspection?

A. 0 percent defectives

B. 4 percent defectives

C. 5 percent defectives

D. 9 percent defectives

E. 22 percent defectives

Answer

This answer is hidden. It contains 27 characters.