Question

The staff training center at a large regional hospital provides training sessions in CPR to all employees. Assume that the capacity of this training system was designed to be 1800 employees per year. Since the training center was first put in use, the program has become more complex, so that 1400 now represents the most employees that can be trained per year. In the past year, 1350 employees were trained. Calculate the efficiency and the utilization of this system.

Answer

This answer is hidden. It contains 75 characters.