The term fast track
a. Is synonymous with design/manage
b. Means that construction is begun before the design is complete
c. Is synonymous with turnkey
d. Indicates that two or more companies have combined forces for the duration of the project.
e. None of the above

Answer

This answer is hidden. It contains 1 characters.