Question

The time an activity will take assuming very unfavorable conditions is:

A) the optimistic time.

B) the pessimistic time.

C) the activity variance.

D) the minimum time.

E) exactly twice as long as the expected time.

Answer

This answer is hidden. It contains 24 characters.