The time taken for guests to check out at a hotel front desk was measured over the course of several weeks. The management believes that the target time for checking out guests should be between 2 and 3 minutes with a target of 2.5 minutes. The data gathered for the actual process had a mean time of 2.75 minutes with a standard deviation of 0.45 minutes. The process capability index will be:

a. less than or equal to 1.

b. more than 3 but less than or equal to 5.

c. more than 4 but less than or equal to 5.

d. more than 5.