There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2 days. The standard deviation of the critical path is:

A. 3.

B. 5.

C. 9.

D. 16.

E. 25.

Answer

This answer is hidden. It contains 64 characters.