Question

Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ________ should be crashed first, adding ________ to project cost.


Activity Normal Time Normal Cost Crash Time Crash Cost
B 4 days $6,000 3 days $8,000
C 6 days $4,000 4 days $6,000

A) B; $2,000

B) B; $8,000

C) C; $1,000

D) C; $2,000

E) C; $6,000

Answer

This answer is hidden. It contains 17 characters.