Question

Under the lot-for-lot (L4L) lot sizing technique as used in MRP, we would expect which of the following?
A. A consistent lag of supply behind demand
B. Minimized carrying costs
C. Minimized set-up costs
D. A just in time management philosophy
E. Minimized quality problems

Answer

This answer is hidden. It contains 1 characters.