Question

Under UCC Sections 2-615(a) and 2A-405(a), a delay in delivery or nondelivery, in whole or in part, is not a breach in circumstances in which performance has been made ______ because a contingency has occurred that was not contemplated when the parties reached the agreement.

A. unreasonable

B. unprofitable

C. less profitable

D. impracticable

E. more difficult

Answer

This answer is hidden. It contains 241 characters.