Question

Using the cut-and-try method for aggregate operations planning we can determine the production requirement in units of product. If beginning inventory is 4,000 units, the demand forecast is 2,900 units and the required safety stock is 10% of the demand forecast, what is the production requirement?

Answer

This answer is hidden. It contains 7 characters.