What does the POQ interval equal?

A) the number of periods of average demand covered by the safety stock

B) the same number of periods that are on the "not to be rescheduled" side of the time fence

C) EOQ / maximum gross requirement

D) the number of periods until the incoming projected on hand runs out

E) EOQ / average demand per period

Answer

This answer is hidden. It contains 35 characters.