Wheeled Coach insists all of the following tasks are key to successful MRP use except

A) materials plan must meet both schedule requirements and facility capabilities

B) plan must be executed as designed

C) inventory investment must be minimized

D) excellent record integrity must be maintained

E) stringent quality control

Answer

This answer is hidden. It contains 1 characters.