Question

When implementing a lean production system a stabilized schedule is achieved using which of the following?
A. Level scheduling
B. Demand pull
C. Freeze window
D. Reduced lot sizes
E. Bottom-round management

Answer

This answer is hidden. It contains 1 characters.