Question

When the operating cash flow of a project is equal to zero, the project is operating at the:

A) maximum possible level of production.

B) minimum possible level of production.

C) financial break-even point.

D) accounting break-even point.

E) cash break-even point.

Answer

This answer is hidden. It contains 1 characters.