Question

Which lot-sizing technique orders the quantity needed during a predetermined time between orders?

A) economic order quantity

B) periodic order quantity

C) lot-for-lot

D) time fencing

E) part-period balancing

Answer

This answer is hidden. It contains 35 characters.