Question

Which of the following are limitations of PERT?

(I) Time estimates may include a fudge factor.
(II) Important activities may be overlooked.
(III) It is an after-the-fact analysis.

A. I and II

B. I, II, and III

C. I and III

D. II and III

E. I only