Which of the following best describes a kill point in the project life cycle?
a. The period of time given to managers during the feasibility phases to decide on the cost, quality, and time constraints for the project
b. A review of the status of a project at each phase of development to determine if it should be continued, redirected, or terminated
c. The point of time in the project lifecycle after which it is impossible to terminate a running project
d. The final submission of the project deliverables after which the project is terminated

Answer

This answer is hidden. It contains 1 characters.