Question

Which of the following is NOT consistent with level scheduling?

A) varying the use of subcontracting

B) finding alternative work for employees during low-demand periods

C) using built-up inventory to meet demand requirements

D) varying production levels and/or work force to meet demand requirements

E) All of the above are inconsistent with the pure level strategy.

Answer

This answer is hidden. It contains 24 characters.