Question

Which of the following is one of the main purposes of a MRP system?
A. Educate personnel in basic work rules
B. To determine time schedules for material procurement
C. Stimulate the work force
D. Decrease labor requirements
E. Increase inventory accuracy

Answer

This answer is hidden. It contains 1 characters.