Which of the following is true about the agile method?
a. It is often used when a project team can express the scope early in the product life cycle.
b. It is used when a project team wants to provide a potentially shippable product earlier rather than later.
c. It uses several iterations or deliveries of software instead of waiting until the end of the project to provide a product.
d. It is used when project teams want to use the predicative approach to a project.

Answer

This answer is hidden. It contains 1 characters.