Question

Which of the following is true of a rough order of magnitude estimate?
a. It is used to allocate money into an organization's budget.
b. It provides an estimate of what a project will cost.
c. Its timeframe is always less than a year prior to project completion.
d. It is a type of estimate that is done in the final stages of a project.

Answer

This answer is hidden. It contains 1 characters.