Which of the following statements is TRUE about the MRP plan when using lot-for-lot ordering?

A) The quantity of gross requirements for a child item is always equal to the quantity of planned order releases for its parent.

B) The quantity of gross requirements for a child item is equal to the quantity of planned order release(s) multiplied by the number of child items used in the parent assembly.

C) The quantity of gross requirements for a child item is always equal to the quantity of gross requirements for its parent.

D) The quantity and gross requirements for a child item is always equal to the quantity of net requirements for its parent.

E) All of the above are true.

Answer

This answer is hidden. It contains 20 characters.