Question

Which of the following takes place during the second stage of a stage-gate development funnel?

A) The product development proposal is reviewed in terms of its fit with the goals and strategies of the organization.

B) A senior management committee reviews the new product development plan.

C) Organizational resources are allocated for developing a prototype of the product.

D) A cross-functional team of managers is formed to develop a detailed plan for product development.