Question

Which one of the following will decrease the net present value of a project?

A) Increasing the value of each of the project's discounted cash inflows

B) Moving each cash inflow forward one time period, such as from Year 3 to Year 2

C) Decreasing the required discount rate

D) Increasing the project's initial cost at time zero

E) Increasing the amount of the final cash inflow

Answer

This answer is hidden. It contains 1 characters.