Question

Which portion of the master production schedule is normally fixed, frozen, or firm?

A) the entire schedule

B) only the aggregate schedule

C) only the middle of the schedule

D) only the near-term portion

E) only the far-term portion

Answer

This answer is hidden. It contains 1 characters.