Question

You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the project "direct costs" are given below.

The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days the total indirect costs are $400, 15 days they will be $250, 14 days they will be $200 and 13 days they will be $100. At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs)?
A. 16 days
B. 15 days
C. 14 days
D. 13 days
E. 12 days