Question

You have just computed a Z=2.55 in a CPM analysis of a critical path for a project. Based on this Z value what is the probability of completing this project on time?
A. 0.76543
B. 0.67543
C. 0.99061
D. 0.99461
E. You cannot tell based on the information given

Answer