Question

You have just performed a Single Time Estimate CPM analysis and have found that more than one path through the project network has zero slack values. What can you conclude?
A. You have incorrectly performed the analysis
B. You have multiple critical paths
C. Only one path is optimal
D. More than one path is optimal
E. The project will not be completed by the desired time