You have run a capacity resource profile on your shop. Products have been routed sequentially through resources A, B, C & D. The capacity resource profile tells you that recourse A is scheduled at 95 percent of capacity, recourse B at 80% of capacity, recourse C at 130% of capacity and recourse D at 100% of capacity. Assuming that the data we used to calculate the capacity resource profile was reasonably accurate, how would you employ the "drum, buffer, rope" thinking?

Answer

This answer is hidden. It contains 399 characters.