Question

Zhang Industries budgets production of 300 units in June and 310 units in July. Each unit requires 1.5 hours of direct labor. The direct labor rate if $14 per hour. The indirect labor rate is $21.00 per hour. Compute the budgeted direct labor cost for July.
A.$6,300.
B.$6,510.
C.$9,450.
D.$9,765.
E.$16,275.

Answer

This answer is hidden. It contains 28 characters.